"The
development of KLIA2 is 98 per cent ready but the biggest test is on the
integration and coordination of airport operations, and that requires third
parties."
Hishammuddin
said the cost of KLIA2, which is built to handle some 45 million passengers
annually, remained at RM4 billion.
He said,
however, the total cost of the project would be revealed after its completion.
KLIA2's completion date has been revised at least three times. The delay was
caused by changes in the job scope that included an increase in the size of the
terminal, installation of a fully-automated baggage-handling system,
construction of an additional 68 gates and 80 aerobridges, and increasing the
height of the air traffic control tower from 77m to 134m.